See below for a schedule of some key milestones within the project:
Feb 2012
Opening of the whole of the CNDR road, A595 to M6.
August 2011
Opening of the northern section of the road into Kingmoor Park.
December 2010
Opening of the new Kingmoor Railway Bridge.
March 2010
Start of construction of the southern section of the new road from the A595 to the River Eden.
December 2009
Demolition of the existing rail bridge at Kingmoor over the West Coast Main Line. Follow this link to view images of the demolision.
November 2009
Flooding led to closure of Workington (Calva) bridge - repairs ongoing. Follow this link for further information
October 2009
Start of construction of the northern section of the new road.
September 2009
Installation of the new temporary rail bridge at Kingmoor over the West Coast Main Line.