Project milestones

Skip main menu

Listed below are the estimated milestones for the construction for Northside bridge.

Please note that these timescales are an estimation only based on the work that is currently ongoing. The works are weather dependant and these dates may change at short notice.

 

Northside bridge milestones
WorksCurrent estimated completion date
Piling worksDecember 2011 - completed
Bridge piersMid January 2012 (excluding stone cladding)
Late January 2012 (excluding stone cladding)
Bridge abutmentsLate January 2012 (excluding stone cladding)
Mid February 2012 (excluding stone cladding)
Steel beam liftsCommence mid Feb 2012 (North side beam erection)
Late Feb 2012 (South side beam erection)
Mid March 2012 (Centre span beam erection)
Bridge superstructure (concrete works)June/July 2012
Highways work (road works)Late June 2012
Opening to trafficMid to late August 2012
Completion (landscaping etc)Mid September 2012