Kendal Infrastructure Improvements

The proposed Kendal infrastructure improvements are part of the Cumbria Local Enterprise Partnership's (LEP) Growth Deal allocation. £ 2.3 million was identified for the delivery of a number of infrastructure improvements in Kendal. These Infrastructure improvements will support the anticipated growth in the area as identified in South Lakeland District Council's Local Plan. Cumbria County Council is delivering the infrastructure improvements on behalf of Cumbria LEP, working closely with SLDC in scheme development and delivery.

Kendal is only 8 miles west of the M6 corridor, which provides Cumbria with excellent regional links, and an attractive location for investment and economic growth. The benefits of this project will not just be restricted to Kendal but spread across nearby villages of Oxenholme, Natland and Burneside.

There are existing highway constraints at key locations in Kendal, particularly in the town center due to narrow streets and congested junctions. The anticipated developments identified in South Lakeland District Council's Local Plan are expected to result in further negative effects on the highway network, therefore there is a pressing need to introduce a number of infrastructure improvements to help support the economic growth of Kendal.

This package of improvements includes junction widening, improved signalisation and traffic management as well as walking and cycling improvements. Together these improvements focus on implementing the necessary infrastructure and transport planning measures across Kendal to reduce vehicle queuing and delay at key locations on the highway network, as a direct impact of new housing and employment allocations in Kendal and surrounding villages

The work has been split into two packages.  Package A mainly focused on junction improvements, while Package B has a focus on sustainable transport, including new cycle routes and traffic calming.

Package A Sections of Work:

COMPLETED

Kendal Parks Road  
COMPLETED: Pedestrian improvements to Kendal Parks Road

Milnthorpe Road/Romney Road
COMPLETED: New pedestrian refuges, traffic signals and resurfacing works

Garth Heads
COMPLETED: Improvements to footway

Parkside Road/Valley Drive
COMPLETED: New traffic signals and resurfacing work.

Highgate/Lowther Street
COMPLETED: Final loop cutting.

Sedbergh Road/Sandylands
COMPLETED: Carriage way widening

Milnthorpe Road/Vicarage Drive
COMPLETED: Resurfacing works

Appleby Road / Sandylands Road
HOLD: Junction improvement - consultation event required prior to establishing the preferred solution for this junction. Consultation will be programmed for when flood affected residents are back in their homes.

Blackhall Road/Stramongate
HOLD: Carriageway widening and new pedestrian island - delayed due to flooding

Parkside Road / Castle Rise
COMPLETED: Footway widening and new footway construction

Appleby Road / Spital Parks
COMPLETED: Footway build-out at junction

Heron Hill/Esthwaite Avenue
COMPLETED: Pedestrian crossing improvements


Package B Sections of Work:

The construction of the Kendal Infrastructure Improvements - Sustainable Transport Schemes began in Autumn 2016 and are due to be completed by Autumn 2018.  This package of work includes;

Longpool/Station Road/Ann Street junction
Summer 2018 - Upgrading pedestrian crossing and resurfacing road

North Kendal Cycle Route
Summer 2018 - The North Kendal Cycle Route, running the length of Shap Road from Morrison's into the town centre.

Burton Road Cycle Route
Phase 1, a cycle route from Kirkbie Kendal School to ASDA Roundabout. Completed 2017.

Phase 2, Cycle Route from ASDA Roundabout to Natland Railway Bridge. Due to be completed Summer 2018.